Asbestos Removal London Case Study - Community Centre Projects

Deconstruct UK - Community Centre Projects

Posted via Industry Today. Are you into it? Follow us on Twitter @IndustryToday

Client: Ayerst Environmental Ltd

Stakeholder: London Borough of Hammersmith & Fulham

Location: Aspen Gardens Community Centre, London W6

Contractor: Deconstruct UK Ltd

Completion Date: April 2011

Sector: Public Buildings

Decontamination of asbestos from boiler house in local community centre.

Asbestos Removal LondonAsbestos Removal London

About the project:

The calorifier vessels and pipework within the boiler room had been subjected to damage over the years and an effective repair was necessary. The damaged pipework was cleaned using h-type vacuum cleaners and 'tac' rags before being repaired using calico wrap and elastomeric paint. The boiler house was thoroughly decontaminated and the timber enclosure to the calorifiers was made good.
 

Project challenges:

This project was undertaken adjacent to a live Community Centre that was in constant use, so it was imperative that our operatives carried out the works as discretely as possible and conducted themselves professionally at all times. The access to the working area was directly off the public highway, so a secure timber hoarding had to be erected around the entrance to the boiler room.

An operative was stationed outside the entrance to the enclosure at all times, during working hours, to ensure that no unauthorised people entered the work area.

Download the Asbestos Removal case study for Aspen Gardens Community Centre here

Our Services:  
Deconstruction Services  
Demolition Services  
Enabling Works  
Asbestos Removal Services tick
Ground Works Services  
Piling Services  
Steelwork Installations  
Builders Works  
Emergency Dangerous Structures  
Temporary Works  
Asbestos Surveying  

For further information about our Asbestos Removal and Deconstruction services, please call 020 7734 6655 or email enquiries@deconstructuk.com

Contact Information

Nicky Frost
18 Generator Hall
Electric Wharf
Coventry
CV1 4JL